CHALLENGING VIADUCT CONSTRUCTION IN SINGAPORE: CONSTRUCTION OF TAMPINES VIADUCT OVER EXISTING ROADS

The construction of the new Tampines viaduct presents some challenges. The installation must be completed in a very tight area with not much space to perform the heavy lifting tasks. As an expert in this area, Hwa Seng Builder Pte Ltd (HSB), a leading civil engineering and construction provider, is called for the job relying on a 70 t telescopic crawler crane from SENNEBOGEN.

The new Tampines viaduct in Singapore connects TPE, Tampines Expressway, to PIE, Pan Island Expressway (Tuas) and Upper Changi Road East. It aims to ease traffic congestion in the area by providing an alternative route for motorists. Overall, the new 1.8 km one-way viaduct will improve traffic flow and reduce travel time for residents in and out of the area, making their daily commute more efficient and convenient.

HIGH SAFETY RE­QUIRE­MENTS FOR THE CRANE

Because the road is still partially active, there have been special safety requirements for the crane. The SENNEBOGEN 673 has met these regulatory requirements. The lifting tasks include the handling of concrete piles, installation of rebar cages, assembling and dismantling of column formwork in tight active public roads. Therefore, the crane needs to be extremely stable to minimize the need of movement around the jobsite. Additionally, the tight job with concrete barriers surrounding the site requires a small footprint. The prior setting of the “virtual wall”, an added safety function that create swing restriction to SENNEBOGEN 673 E allows the operator to focus on the task at hand and not to worry about the concrete barriers, making the SENNEBOGEN crane perfectly equipped for these delicate operations. Another criterion that led Hwa Seng Builder Pte Ltd to opt for the SENNEBOGEN 673 E for the project. The Full Power-boom that can telescope under load thus avoiding the need to move the for most tasks.

LIFTING OPERATIONS ABOVE THE ROAD: SAFE LIFTING THANKS TO THE CRANE’S STABILITY

The formwork and other materials to be lifted weigh about 2 t each and have odd shapes, that can easily be caught by the wind. These circumstances can complicate the lifting tasks very quickly. Luckily the sturdy 70 t telescopic crawler crane, sitting on a 4.8 m track when fully extended provides maximum stability. Together with the well-built robust boom, swaying activities are greatly minimized.

“A fair amount of my lifting tasks is below 30 m high. The SENNEBOGEN 673 E fits perfectly on the sweet spot between being on the right capacity and boom length that will not cost an excess overweight. A big advantage compared to other crane types which usually have plenty of excess weight.” Tee Ley Shui, Crane Operator.

 

Quick movement between jobsites

Sia Wee Hong Raymond, the logistic coordinator for SENNEBOGEN 673 E explains: “As the columns for the viaduct are in between the main road, we have to move the SENNEBOGEN 673 E telescopic crawler crane almost every day from site to site depending on the lifting schedule, the retractable undercarriage and being able to load up and down the lowbed trailer with its counterweight is indeed a time saver.”

Working together with Raymond Sia is Ce Zhuang fromAly Energy Singapore, the SENNEBOGEN dealer in Singapore. Ce Zhuang actively communicates with Raymond, supporting especially in after sales service.

“ALY Energy has been supporting HSB closely for more than 6 years which give me the confidence in deploying SENNEBOGEN cranes to complicated jobsites.” Sia Wee Hong Raymond, logistic coordinator, HSB.

 

 

Attachments

Related Post

thumbnail
hover

Liebherr delivers high-quality ship to shore...

This is the third Liebherr STS at PSA Penn Terminals in the Port of Philadelphia. Crane designed and manufactured in Ireland and delivered t...

thumbnail
hover

Bruks Siwertell commissions second Siwertell ship...

Bruks Siwertell has completed the installation and commissioning of a second Siwertell screw-type ship unloader for leading Indian fertilize...

thumbnail
hover

Customers meet the new-design Konecranes Noell...

On Thursday the 26th of September,  Konecranes was privileged to receive an eminent group of straddle carrier customers at its  straddle c...

Leave us a comment

logged inYou must be to post a comment.